Port-au-Prince, 4 November 2011 – Two-and-a-half million  dollars (US$2.5 million) to supply water to several marginal  neighborhoods in the capital. Approved in 2006. But, five years later,  the water isn’t running yet. Children are still in the streets bearing  bottles and buckets.
The project is almost finished. “The end of October,” according to the funder. But not yet.
Why? And why five years? Haiti Grassroots Watch (HGW) and the  students at the State University’s Faculty of Human Sciences  investigated.
Unavoidable liquid, inescapable burden
There’s a new reservoir, pipes, and over a dozen water fountains, but  the people who live in the poor neighborhoods of Debussy and Upper  Turgeau still have to walk for long hours to obtain this live-saving  resource. During their daily pilgrimage, the adults and children – who  are sometimes only five or six years old –  pass by the dry water  kiosks.
Tercy, a university student, lives in Georges City, one of the  miserable and informal neighborhoods of Turgeau. He shares a little  cement block hut with his sister. Among his other daily activities,  Tercy (who didn’t want to reveal his last name), said he has to get up  very early to get water before going down to the faculty.
“I leave home at 5:35 am to get two gallons of water. Now its almost 7  am,” he continued, wiping the sweat from his face. Only after the long  trek can he bathe and prepare to go to the classroom.

A young boy on one of his daily water 
trips.  [Photo - James Alexis]
Emmanuel Lima, carrying a full bucket on his head, relayed the same  comments. Alluding to the unfinished water project, he said that “it  will be a good opportunity for the neighborhood, but they are taking too  long to finish it.”
“In this country, those in power are too negligent. They don’t take  care of the really important thing. Everyone just wants to get rich,”  the 42-year-old said indignantly.
Lima and Tercy are among the two-thirds of the capital region’s  population that has to get their water in buckets, according to 2002  data from the Haitian Institute of Statistics and data processing.
The European Union’s gift of water
In 2006, the European Union (EU) gave the green light to a water  project for Debussy and Turgeau, neighborhoods populated by about 25,000  people jammed into huts, many of them on dangerous slopes.
The project’s principal elements:
• A new reservoir in the Debussy hills
• A connection between the new reservoir and the Upper Turgeau reservoir
• A pump for the Upper Turgeau reservoir
• 19 water kiosks in various neighborhoods
• Pipes linking the new reservoir to the fountains
 

Google map showing the location of the Turgeau reservoir, the new Debussy reservoir, 
and the neighborhoods that will benefit (encircled in yellow).
The supervision of the project’s execution was overseen by the following three entities:
The state - The Autonomous Central Metropolitan Water Authority (Centrale  Autonome Métropolitaine d’Eau Potable - CAMEP), today called the  National Direction of Drinking Water and Sanitation (Direction Nationale de l'Eau Potable et de l'Assainissement - DINEPA) 
The EU - The Technical Unit for Rehabilitation Programs (L’Unité Technique des Programmes  de Réhabilitation - UTPR), 
A French "non-governmental organization" (NGO), the Group for Research and Exchange of Technologies (Groupe de Recherche et d'Echanges Technologiques - GRET), which has worked in the area of water in Haiti since 1995.
According to Benoist Bazin, head of the EU’s Infrastructure Section  in Haiti, the total cost of the project was about 100 million gourdes or  about US$2.5 million. One-quarter, about 25 million gourdes  (US$625,000) was spent on the new reservoir and 75 million went for the  rehabilitation of the water system by two private companies, and for  « social accompaniment » carried out by GRET.
Maxo Saintil, a professor living in the Upper Turgeau area, was among  the group of people who, over five years ago, asked the government of  put in a water system in order to assuage people’s misery over five  years ago. 
In 2006, he was happy to hear the project had been approved.
"The completion of the project will be a victory for us, the  initiators, and it will benefit the population who will benefit from its  service," he told HGW.
But between the approval and the beginning of work, three years went by.
"The project only started in January, 2009," Saintil remembered.
And 34 months later, the project is still not complete. There are  many reasons… and an examination of them will allow the reader not only  to learn the "why" but also to learn how "development aid" sometimes  works in Haiti.
Studies stumbling blocks
At the beginning, CAMEP, the state organism asking for financial  assistance, hadn’t done a study that was well focused nor was it  sufficiently in-depth.
According to Robenson Jonas, Léger, coordinator of the EU’s UTPR, the CAMEP report was "incomplete."
“We had to order a complete reservoir study,” Léger wrote to HGW in an email.
The first study recommended a 1,200 cubic meter reservoir. That  study, and a geotechnical study cost 246,093.63 gourdes or US$6,152.34.
According to Léger, CAMEP approved the study but at the moment work  was about to begin, supervisors expressed certain worries, since the  study didn’t account for a possible earthquake. The proposed reservoir  was to be elevated above the ground, on supports.
“This was in 2007, and this was a good anticipation of the January 12, 2010, earthquake,” Léger noted.
The second study cost 343,440 gourdes (US$8,586) and was finished on  March 19, 2008, two years after the project was originally approved. The  second study called for a reduction in the reservoir’s size, from 1,200  to 900 cubic meters, “in order to stay within the limits of the  available budget,” according to Léger. The study recommended a reservoir  that sat on the ground, which is more expensive.

 

The Debussy reservoir. [Photo courtesy of WASH Cluster]
The TECINA company signed the contract for design and construction,  for 24,073,324.22 gourdes (US$601,833), or about one-quarter of the  total budget. But work didn’t begin immediately.
“The work started one year after the signature of contracts,” social  worker (and now director) Jean Ledu Annacacis of GRET remembered. If he  remembers well, in March 2009.
Nine months later, in December 2009 according to Léger, the work was almost finished. But not yet.
The water still wasn’t flowing.

 
A kiosk with dry faucets. [Photo - James Alexis]
Disbursement Delays
According to all the actors, there was also a delay in the disbursement of funds which postponed the completion of the project.
Engineer Raphael Hosty, director of the West Department’s office of  DINEPA, the state agency that replaced CAMEP, told HGW that the project  was slated to take 18 months overall. And that even the necessity of two  studies should not have delayed the project so much. According to  Hosty, TECINA and the other companies stopped working in December, 2009,  because the payments stopped flowing.
Chandler Hypolite, a field agent for GRET, said the neighborhood  committees – responsible for managing the water kiosks – were ready to  start by the end of December, also.
But the work stopped.
“The companies working on the project stopped receiving money,” he  said. “They refused to work… the project came to a halt before the  January 12, 2010, earthquake.”
GRET’s Annacacis told the same story.
“I know that [the companies] didn’t get the money they needed to complete the work,” he remembered.
“There was no problem of financing,” the UTPR’s Léger told HGW.  “There was perhaps a delay in payment… because in the meantime, we were  changing the computer system, which slowed down some of our casework.”
And then – the January 12, 2010, earthquake. Another delay. Not in  terms of damage, but because after the disaster the EU had –  legitimately – other priorities for many months.
Customs Delays
In addition to the disbursement delays, the Haitian customs office is  partly responsible for the slow progress of the project, according to  many of the actors, who noted that material was blocked for months.
Not surprisingly, since Haiti’s port and customs offices are world famous for their inefficiency and corruption.
A study by the World Bank cited by the Miami Herald showed that Haiti’s port costs businesspeople and importers twice what  they pay in the Dominican Republic, and that getting material out of  customs can take three times as long.
Cited in the same article, published in July, 2010, Hughes  Desgranges, a senior advisor to the National Port Authority, admitted  that the port is more of a “social program” than a “commercial program”  because of the salaries paid to “ghost” employees or employees who  weren’t necessary.
“You have a port that can be the engine of the Haitian economy, but it's been badly steered,” he said.
Everyone participating in the water project criticized customs, like Hypolite, who criticized: “the pumps were blocked.” 
 Woman with a five-gallon bucket. [Photo - James Alexis]
Woman with a five-gallon bucket. [Photo - James Alexis]
Project almost finished, but the water’s still not flowing
Finally, almost two years later, the work is almost finished, but  progress has been very slow. Workers don’t come every day and the end  date of October 31 was missed. (However, there are indications that the  water will start to flow within the coming weeks.)
“The delays in connecting the reservoir with the pipe network weren’t  small,” the EU’s Bazin admitted in an interview with HGW on September  27, 2011. “Today the situation is this - the firm need to install the  valves on the back of the reservoir that will assure it fills and  functions normally.”
Bazin’s frustration was clear.
“When things go well, they never say its because the EU did  everything possible to make it work,” Bazin said with an ironic tone.  “The same way, one shouldn’t blame the EU [only] when things go badly.”
The reasons for things “going badly” are many – delays in disbursements, at customs, and the two studies.
But could it also be because of the multiplicity of actors? Several  government agencies, of the EU, an NGO and three private firms… 
And why was three-quarters of the budget (75 million gourdes or about  US$1.875 million) used for the “rehabilitation of networks” and “social  accompaniment?” Why were the budgets adjusted after the second study so  that a 1,200 meter-cubed reservoir could still be constructed?
HGW could not look into all aspects of this complex project, but it’s  probable that the blame does not rest with merely one or another actor.  While the percentages of the blame are not known, several things are  certain. There is a new reservoir, but with one-third less capacity than  initially planned. There are kiosks. And pipes.
But the implementation of a good solution to a daily challenge for  25,000 people has taken more than five years instead of 18 months, and  it has a reduced capacity for what is probably a larger population.

While one boy heads off to school, two young women carry water. [Photo - James Alexis]
Nadège Thermilus, a young unemployed 22-year-old woman, has big  hopes. Like her friends at her side, she’s on her way to draw water at a  place they call “in the mountains,” perhaps about two hours away,  round-trip.
Before heading back up to “in the mountains,” she says: “I hope the  water comes, because I’ve lived too much misery going to get it.”
 
Students from the Journalism Laboratory at the State University of Haiti collaborated on this series. 
Haiti Grassroots Watch is a partnership of AlterPresse, the  Society of the Animation of Social Communication (SAKS), the Network of  Women Community Radio Broadcasters (REFRAKA) and community radio  stations from the Association of Haitian Community Media.